dic 07, 2021

Challenges to open pit mining through historic underground workings

  • Artículo
  • open pit mining
  • underground mine workings
  • hazard awareness

Mining operators are increasingly looking into developing large open pits down through old, abandoned underground workings to extract remnant ore left within pillar zones. However, maintaining pit wall stability while mining through a large network of underground mine workings isn’t easy and has its risks that can significantly impact overall pit economics and viability.

  1. The interactions between the stopes and pit walls may present operational challenges, requiring pit wall redesign, ground support installation and operational rescheduling. Anticipated interactions of the pit shell with the mine workings must also be closely evaluated to maintain a safe working environment.

    Open pit interaction with underground mine workings

    The interaction of the pit with previously mined stopes presents a challenge to stability design in the walls and pit floor. An example of stope exposure in the pit wall is provided in Figure 1.

  2. Stopes are assessed on a case-by-case basis, with special attention given to those that may impact the pit ramp or catch benches due to their location, dimensions or compromised rock mass stability. In addition, the exact position of individual stopes may be unknown due to incomplete mine records.

    Defining voids

    Voids are identified and defined using a variety of sources, including historic mine plans and sections, stope records and probe drilling. Where conditions permit, larger voids are surveyed using a borehole scanner.

    Voids fall into three categories:

    1. Stopes and lateral or vertical mine development that will daylight or lie adjacent to the designed open pit highwall. The stability of these problematic stopes is assessed using a range of techniques including kinematic analyses, analyses of potential support demand and numerical modelling to evaluate overall stability interaction issues.
    2. Mine workings that will be intercepted by the advancing pit floor. Based on proximity to voids, the pit floor can be subdivided into non-restricted, cautionary and restricted areas to ensure personnel safety.
    3. Stopes and mine workings that lie well beyond (30 m+) the ultimate pit shell design.

    Stability design tactics

    Ground support or pit geometry re-design is used to establish stable wall conditions when near or intercepting historic mine workings.

    Ground support

    Ground support measures include:

    • Rock mass is reinforced with cable bolting or rock bolting.
    • Surface cover is used by draping screening over the wall to mitigate rock fall risk at locations where catch bench geometry has been compromised.
    • Backfill exposures are stabilized by replacing existing unconsolidated fill (typically fines or sand) with a cover of waste rock, allowing a steeper angle of repose.
    • Voids are backfilled in advance of pit mining. Depending on proximity to the ultimate pit shell, unconsolidated or consolidated backfill is used.
    • A minimum pillar dimension requirement is maintained above voids, with undersized sill pillars blasted down. In the case of large open stopes, drop raises may be used to fill the underlying void with broken waste muck prior to blasting down the sill.

    Pit wall geometry redesign

    Pit wall geometry is redesigned to minimize the impact of voids on pit wall stability. Figure 2 shows an example of pit redesign around a stope. Design measures include:

    • Stepping the final pit wall around the mine workings
    • Increasing or decreasing bench face angles and berm widths
    • Changing the ramp width or grade
    • Changing the location of the ramp (in extreme cases)
  3. Hazard awareness

    In addition to hazards associated with pit wall stability, subsidence is also a significant concern when working near historic mine workings. It can be triggered by ground thaw, heavy rain and nearby pit blast vibrations.

    Areas where subsidence is anticipated are typically identified by physical barriers (such as temporary berms) and delineator cones and pickets. Safety procedures at the mine dictate which areas can be accessed and what precautions are required.

    Conclusion

    The design and stability of open pits developed through historic underground workings are influenced by “typical” factors, such as rock mass and structural characteristics, and by “atypical” factors in the form of underground mine workings.

    To anticipate and mitigate risks, voids intersecting the pit wall and floor are identified, defined and assessed. Pit designs are adjusted around anticipated and intercepted workings, and revised designs may require ground support.

    If you are looking for solutions to your open pit challenges, we can help! Reach out to our rock mechanic experts.

This content is for general information purposes only. All rights reserved ©BBA

Publicaciones más recientes
Ver todo
Let’s
think it further
together
Póngase en contacto con nosotros