Engineering and commissioning 34 wind turbines in the Gaspé

  • Project
  • wind power
  • wind farm
  • wind turbines
  • commissioning
  • hydro-quebec
  • detailed engineering
  • project management
  • substation
  • FATS
Project Page Hero 34 wind turbines Gaspe

Invenergy designs, owns and operates major renewable power plants in North America and Europe. Creating the Roncevaux wind farm, which started operating in 2017 in the Gaspé, was part of its business development strategy.

  • Region Eastern Canada
  • Client Invenergy Wind LLC
  1. Our experts' solutions

    BBA performed the detailed engineering, project management and commissioning of the electrical substation and collector system for the Roncevaux wind farm, a 75 MW power plant composed of 34 wind turbines interconnected to Hydro-Québec’s 315 kV grid. BBA mitigated risks at the site by performing factory acceptance tests (FAT) on control panels and on the protection devices of control buildings.

    BBA team members provided the developer with technical support to connect the wind farm to the Hydro-Québec grid while meeting the agreed energization date. Our experts ensure coordination among project stakeholders (developers, contractors, turbine manufacturers and Hydro-Québec) to perform testing and commissioning.

    • Project management
    • Various studies
    • Technical equipment specifications
    • Detailed engineering of substations and collector systems
    • Electrical installations
    • Control and protection supervision
    • Basic engineering for SCADA systems
    • Collector system and electrical substation commissioning
    • Downstream interconnection of the main 315 kV circuit breaker with another existing wind power substation that is very difficult to access
    • 34 2.2 MW wind turbines
    • 75 MW Farm totalling 75 MW
    • 315 kV Connected to a 315 kV Hydro-Québec grid